Ontario Northland, an Agency of the Province of Ontario, was established in 1902 and is a recognized leader in promoting sustainable economic growth by establishing and operating transportation links, primarily in Northeastern Ontario. With approximately 1,000 employees who live and work in the North, Ontario Northland, and the economic activity it stimulates, has a dramatic impact in the region.
Ontario Northland maintains over 100 bridges and 2000 culverts spread across 700 miles of track exposed to the Northern Ontario climate. Ontario Northland is replacing the Middle Mulock Creek Bridge, located at Mile 17.65 on the Temagami Subdivision, with 2 – 1970mm I.D. culverts and the North Mulock Creek Bridge, located at Mile 17.95 on the Temagami Subdivision, with 2 – 1200mm I.D. culverts. We are requesting proposals for the culvert replacement projects at these locations (see Appendix 1). Contractors are invited to submit bids on the tender. The work is scheduled to commence in June 2017 and to be completed by August 31, 2017. All submissions must be submitted by:
2:00 p.m. local time on May 19, 2017
The work includes but is not limited to the removal of the existing 3.0m single bridge spans at Miles 17.65 & 17.95 on ONR’s Temagami Subdivision, the supply and installation of two CSP culverts, Type II Steel with a 2-layer Thermo Plastic Copolymer coating, the supply and installation of concrete knee walls, geotextile, granular bedding, granular backfill, geotextile and rip rap in accordance with Schedule A and the Contract Documents. The sites are located near North Bay, District of Nipissing, Province of Ontario at the Ontario Northland’s Bridge.
Mandatory Site Visit – May 9, 2017 – Register by May 8, 2017.