B3 SITE INVESTIGATION
B3.1 Further to C3.1, the Proponent may view the Site without making an appointment.
B3.2 The Proponent shall not be entitled to rely on any information or interpretation received at the
Site Meeting unless that information or interpretation is the Proponent’s direct observation, or is
provided by the Contract Administrator in writing.
B3.3 The Proponent is responsible for determining:
(a) the location of any utility which can be determined from the records or other information
available at the offices of any public authority or person, including a municipal corporation and
any board or commission thereof, having jurisdiction or control over the utility;
(b) the nature of the surface and subsurface conditions at the Site;
(c) the location, nature, quality or quantity of the materials to be removed or to be employed
in the performance of the Work;
(d) the nature, quality or quantity of the Plant needed to perform the Work;
(e) all matters concerning access to the Site, power supplies, location of existing services,
utilities or materials necessary for the completion of the Work; and
(f) all other matters which could in any way affect his/her Proposal or the performance of the
Work.