D3. SCOPE OF WORK
D3.1 The Work to be done under the Contract shall consist of two parts:
(a) Part 1 – City Funded Work
(b) Part 2 – Manitoba Hydro Funded Work.
Part 1 – City Funded Work
D3.2 Part 1 – City Funded Work shall consist of:
(a) Concrete Reconstruction
(i) McGregor Street from Mountain Avenue to Church Avenue; and
(ii) McGregor Street from McAdam Avenue to Seven Oakes Avenue.
Part 2 – Manitoba Hydro Funded Work
D3.3 Part 2 – Manitoba Hydro Funded Work shall consist of:
(a) Street Lighting and Associated Work
(i) McGregor Street from Mountain Avenue to Church Avenue; and
(ii) McGregor Street from McAdam Avenue to Seven Oakes Avenue.
D3.4 The City currently has no approved funding in the Capital Budget for Part 2 of the
Work, but is anticipating receiving notification about funding from Manitoba Hydro. Part 2 of the
Work is contingent upon Manitoba Hydro approving sufficient funding.
D3.4.1 Further to C7.1, if notice of sufficient funding is not received, the City shall
have the right to eliminate all or any portion of Part 2, and the Contract Price will be reduced
accordingly.
D3.4.2 Further to C7.5, C7.5.1, and C7.6, a reduction in the Contract Price pursuant to
D3.4.1 shall not be considered in calculating the aggregate reduction in the Contract Price for
purposes of C7.5.
D3.4.3 If all or any portion of Part 2 is eliminated pursuant to D3.4.1, the time
periods stipulated in D20.1 for Substantial Performance of the Work and in D22 for Total
Performance of the Work will be reduced proportionally by the Contract Administrator acting
reasonably.
D3.5 The major components of the Work are as follows:
(a) Concrete Reconstruction
(i) Removal of Existing Pavement;
(ii) Excavation;
(iii) External Point Sewer and Manhole Repairs;
(iv) Installation of catch basins and sewer service pipe;
(v) Watermain Service Insulation;
(vi) Compaction of sub-grade;
(vii) Installation of subdrains;
(viii) Placement of separation/ filtration geotextile fabric and Class A geogrid;
(ix) Placement of sub-base and base course (Granular A) materials;
(x) Adjustment of existing manholes and appurtenances;
(xi) Installation of Traffic Signals conduit, service boxes, and concrete bases;
(xii) Construct integral concrete barrier curb (180 mm height) and modified barrier curb;
(xiii) Construction of 250 mm Plain Dowelled (31.8 mm dowels) by slip form paving and 150 mm
Reinforced Concrete Pavements;
(xiv) Construction of 100 mm Concrete Sidewalk with Block Outs for Paving Stone Indicator
Surface; and
(xv) Topsoil and Sod.
(b) Street Lighting and Associated Work
(i) Removal of existing street lighting poles;
(ii) Installation of concrete bases; and
(iii) Installation of new street lighting cables (trenching, boring, and/or overhead) and poles
(including connections).