-The Intent of the project is to prepare courtrooms to be equipped with AV Technology as per JVN/SOLGEN Facilities Scope of Work (FSOW) and Built Ready Drawings.
-The overall scope of work for the project will go beyond the FSOW in order to have the necessary electrical/conduiting, cabling for data (where applicable), power management, architectural & interior finishes, patch & paint and environmental DSS abatement as
required to complete the work.
- Millwork scope includes modification to dais, installation of plywood backing and nut inserts for mounting of monitor brackets.
- Setting up tracks for cabling, walls and ceiling repairs post conduit installation, fire caulking to be applied to any conduit through wall penetrations, paint and make good all walls and flooring as required.
- The new equipment (Microphones, video, screens, speakers, servers, racks, etc.) will be procured, delivered, installed and commissioned by SOLGEN-JVN (as Owner Supplied Equipment) with a 1-week timeframe after the courtroom is presented in ready for
takeover condition.
- MAG (FMB)/SOLGEN-ETG/JVN to be consulted through all phases of the project during design and construction works.
- All works in the courthouse/courtrooms to be completed after hours with a security escort guard.
- Rack/Servers are to be installed in courtrooms or IT closets. Heat from the new equipment in server rooms and racks will need to be reviewed by mechanical/ engineer to ensure sufficient ventilation/AC is provided.